26/11/25 Structural Engineer Site Visit Problem with foundations dug collapsing of soil
28/11/25 Foundations Site Inspection Report Water in cavity - high water table
3/12/25 Foundation Design Strip foundation and Raft
4/12/25 Foundations approval Strip foundation agreed
5/12/25 Foundations Extra to remedy Water in cavity - high water table
9/12/25 Foundations Extra to remedy Dig out and replace with membrane and 4 inches concrete
12/12/25 Block and Beam installing over cavity Showing construction of block and beam prior to building regulator inspection
17/12/25 Block and Beam Site inspection report by building regulator
21/12/25Foundations Ventilation Proposal to cut out the concrete infil to expose the two airbricks installed for conservatory in 2011
30/12/25 Foundations Ventilation airbricks exposed 2 airbricks exposed allowing ventilation from front to back of existing property/extension cavity through to garden